Jackson-Stops & Staff, Estate Agents and Property Consultants, commissioned us to manufacture and install a replacement shopfront in utile hardwood at their High Street office in Dorking. In order to minimise disruption to the business, it was critical that the installation be completed within a two day period on 12th and 13th June with the closure of the office for the first day only and ensuring safe public access on the second day. On the first day the existing shopfront was removed and replaced with the new one fully glazed to leave the shop secure overnight. All work was successfully completed on the second day, all within 48 hours as promised.

‘On behalf of all of us concerned, we are very grateful for the work done and the courtesy and communication extended throughout.’ Colin Hughes, FNAEA for Jackson Stops & Staff